Revised Timetable for Valley Creek Road Construction (Updated)

Washington County sent out an update on Wednesday, Nov. 7.

Below is the latest update from Washington County on the Valley Creek Road construction project.

There will be multiple traffic changes along Valley Creek Road during the next week as crews complete concrete work from Bielenberg Drive to Interlachen Parkway.

Thursday, Nov. 8: The Radio Drive and Valley Creek Road intersection will be closed beginning at 9 a.m. and will be open by 5 a.m. 
on Friday, Nov. 9.  Right turn lanes will remain open.

Nov. 5-7: Mill and overlay will be done from Interlachen to Woodbury Drive. Intermittent lane closures will occur.

Saturday, Nov. 10: Complete project, all
l lanes will open.
 

As always, the schedule is subject to change due to unforeseen conflicts or weather.  

Again, thank you for your patience during construction and as always, please use caution as you travel through the construction.

More information on the project can be found on the project website at www.co.washington.mn.us/valleycreekroad. Questions pertaining to the project and the upcoming meetings may be directed to Jacob Gave, Washington County Project Manager, 651-430-4316 or Jacob.Gave@co.washington.mn.us or Lyssa Leitner, Washington County Business Liaison, 651-430-4314 or Lyssa.Leitner@co.washington.mn.us.

Follow @ValleyCreekRoad on Twitter for construction updates.

 

Like Patch on Facebook | Follow us on Twitter | Sign up for our free newsletter

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something