Valley Creek Road Construction Update

Washington County officials sent out the latest news about the project on Wednesday.

The Valley Creek Road construction project is moving ahead.

Washington County officials on Wednesday sent out the latest update:

Paving between City Centre Drive and Donegal Drive/Central Park Place is complete. The signal at the Valley Creek Road and Radio Drive intersection is operational and all movements are accommodated.

Find out what's happening in Woodburywith free, real-time updates from Patch.

The Contractor will be working on the eastbound lanes (south side of the road) during the next phase of the project.Traffic will be switched to the westbound lanes (north side of the road), one lane in each direction. The traffic control switch will be made early (Thursday) morning (8/23/12) before rush hour. 

Traffic will switch to the westbound lanes at Bielenberg Drive and Colby Lake Drive. Tower Drive will remain accessible for the first part of this phase. City Hall access is maintained, but will be restricted to right-in, right-out. Any changes will be updated prior to the change. 

Find out what's happening in Woodburywith free, real-time updates from Patch.

Thank you for your patience and use of caution while traveling through the project area. 

More information on the project can be found on the project website at www.co.washington.mn.us/valleycreekroad. Questions pertaining to the project and the upcoming meetings may be directed to Jacob Gave, Washington County Project Manager, 651-430-4316 or Jacob.Gave@co.washington.mn.us or Lyssa Leitner, Washington County Business Liaison, 651-430-4314 or Lyssa.Leitner@co.washington.mn.us.

Follow @ValleyCreekRoad on Twitter for construction updates.